Fowlers and Cleveland Roads Upgrade

Share Fowlers and Cleveland Roads Upgrade on Facebook Share Fowlers and Cleveland Roads Upgrade on Twitter Share Fowlers and Cleveland Roads Upgrade on Linkedin Email Fowlers and Cleveland Roads Upgrade link

Consultation has concluded

We're planning for some major road upgrades to Fowlers Road (South) and Cleveland Road in Dapto. The improvements will include road-widening, new shared paths, stormwater works, intersection upgrades, street lighting and planting.

This project forms part of our long-term vision for West Dapto. Improving key access roads will safely meet the demand expected with population growth in the area and grow and develop West Dapto into a series of integrated and connected communities.

We’ll be starting staged construction in early 2025 and expect it will take a few years.

The works will be completed in three stages.


Stage 1: Proposed to start Second Quarter of 2025  

Fowlers Road (South) – formerly known as Daisy Bank Drive, will be widened from 2 to 4 travel lanes. Have a look at the Consultation Plans for Stage 1 here and learn more about Stage 1 construction here.

Stages 2 and 3: Pending land acquisition 

Cleveland Road - approximately 2.5 km stretch of road North from Fowlers Road intersection will be regradedwidened and additional travel lanes/kerbside parking added. Have a look at the Consultation Plans for Stage 2 and Stage 3 here and learn more about Stage 2 and 3 construction here. 

The upgrades to roads will also include kerb and gutter, stormwater works, shared paths and street lighting. 

We'll be working closely with the community to manage the impacts of construction during all stages.

To find out more, take a look at the

You can also see hardcopy information and plans at Wollongong and Dapto Libraries. 

We'll be holding a Drop-In Info session, where you can come and have chat with Council staff about this project.

If you have any accessibility needs or require further support to attend this drop-in, please call 4227 7111.

Share your thoughts 

We’re keen for you to share your local knowledge that we can consider during the construction period. 

You can either complete the online feedback form, email us at engagement@wollongong.nsw.gov.auor call the Engagement Team on (02) 4227 7111. 

The last day to submit feedback is Thursday 7 November 2024. 


If you’re D/deaf or have a hearing or speech impairment, you can contact us through the National Relay ServiceIf you need an interpreter, you can contact us through theTranslating and Interpreting Service on 131 450. You’ll need to provide our phone number (02) 4227 7111 for either service. 

Submissions become public documents and may be viewed by other persons on request. Please read Council's Privacy Policybefore submitting your feedback. 


This project is proudly co-funded by Restart NSW.



We're planning for some major road upgrades to Fowlers Road (South) and Cleveland Road in Dapto. The improvements will include road-widening, new shared paths, stormwater works, intersection upgrades, street lighting and planting.

This project forms part of our long-term vision for West Dapto. Improving key access roads will safely meet the demand expected with population growth in the area and grow and develop West Dapto into a series of integrated and connected communities.

We’ll be starting staged construction in early 2025 and expect it will take a few years.

The works will be completed in three stages.


Stage 1: Proposed to start Second Quarter of 2025  

Fowlers Road (South) – formerly known as Daisy Bank Drive, will be widened from 2 to 4 travel lanes. Have a look at the Consultation Plans for Stage 1 here and learn more about Stage 1 construction here.

Stages 2 and 3: Pending land acquisition 

Cleveland Road - approximately 2.5 km stretch of road North from Fowlers Road intersection will be regradedwidened and additional travel lanes/kerbside parking added. Have a look at the Consultation Plans for Stage 2 and Stage 3 here and learn more about Stage 2 and 3 construction here. 

The upgrades to roads will also include kerb and gutter, stormwater works, shared paths and street lighting. 

We'll be working closely with the community to manage the impacts of construction during all stages.

To find out more, take a look at the

You can also see hardcopy information and plans at Wollongong and Dapto Libraries. 

We'll be holding a Drop-In Info session, where you can come and have chat with Council staff about this project.

If you have any accessibility needs or require further support to attend this drop-in, please call 4227 7111.

Share your thoughts 

We’re keen for you to share your local knowledge that we can consider during the construction period. 

You can either complete the online feedback form, email us at engagement@wollongong.nsw.gov.auor call the Engagement Team on (02) 4227 7111. 

The last day to submit feedback is Thursday 7 November 2024. 


If you’re D/deaf or have a hearing or speech impairment, you can contact us through the National Relay ServiceIf you need an interpreter, you can contact us through theTranslating and Interpreting Service on 131 450. You’ll need to provide our phone number (02) 4227 7111 for either service. 

Submissions become public documents and may be viewed by other persons on request. Please read Council's Privacy Policybefore submitting your feedback. 


This project is proudly co-funded by Restart NSW.



Consultation has concluded
  • Update

    Share Update on Facebook Share Update on Twitter Share Update on Linkedin Email Update link

    We're expecting to start Stage 1 of these road upgrades (Fowlers Road - South) in mid-March 2025.

    Keep an eye on the West Dapto Projects | City of Wollongong page to stay updated on this and other projects happening around the area.