Works update 1 June 2021
Jersey Farm Road to Smith Lane
Shared path: Shared path construction on the northern side of Wongawilli Road has been going well and is expected to be finished this Friday. We'll then work with property owners to organise the construction of several retaining walls along here.
Road reconstruction: We'll be moving to Jersey Farm Road next Monday to start concrete reconstruction works which should be finished by Friday. We'll then start on asphalt resurfacing works the following week. Resident access will be maintained at Jersey Farm Road under traffic control while the works are taking place.
Shone Avenue to Smiths Lane
New layout of temporary road: Excavations have started to create the new alignment for the temporary road near the culverts. Traffic will be diverted onto this newly laid out road in the upcoming weeks. This will allow Cadifern to undertake the final storm-water connections.
Trunk drainage: Works are progressing well and nearing final connection to the existing drainage.