Works update 1 March 2021
Our crews have completed the road drainage crossings and have started drainage works on the north side of Wongawilli Road between Smiths Lane and Jersey Farm Road.
Towards Shone Avenue, we received the first delivery of culverts last Friday. We'll be working this week to finish culvert installation and back-filling on the north side of the road. We'll also be undertaking some preparation works on the south side of the culverts for the temporary realignment of the road during the water main connection. We are expecting the confirmed water main connection date back from Sydney Water shortly.