Works Update 10 March 2022

The weather has been a persistent factor for crews working throughout the Wollongong region including Wongawilli Road. However, progress continues. This month Council crews have constructed almost all the traffic blisters along Wongawilli Road. There are three left complete.

After these are completed, we can move on to finishing storm water drainage work and measures to direct water flow during extreme weather events at the western end. Then the final piece of Kerb and gutter connecting new driveways will be completed.

At the eastern end, Cadifern is lowering the water main and finishing off stormwater inlets and outlets to make way for the upgrade of Shone Avenue.

Please ensure you take care passing through the construction area and consider traffic management measures that may need to be put in place.

Share Works Update 10 March 2022 on Facebook Share Works Update 10 March 2022 on Twitter Share Works Update 10 March 2022 on Linkedin Email Works Update 10 March 2022 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>