Works update 11 August 2022

Wongawilli Road

Work is continuing on the western end of Wongawilli Road. Crews have completed the kerb and gutter on one side and are now working on the other side.

Construction will soon begin on the “earth bund wall” that is designed to divert stormwater towards drainage pits. Council is working with the RFS and the Community Hall to coordinate access to their buildings to undertake the work

West Dapto Road

Work to relocate two watermains has been completed. Currently Council is waiting for approval from Sydney Water to finalise their connection into the water system

Tenders have been received for the first part of work to upgrade West Dapto Road and a preferred contractor identified.

Share Works update 11 August 2022 on Facebook Share Works update 11 August 2022 on Twitter Share Works update 11 August 2022 on Linkedin Email Works update 11 August 2022 link