Works update 12 January 2021

Our works crews and project team are back! Happy New Year Wongawilli!

Our primary focus for the coming month is to address the intersection at Jersey Farm Road. We have more stormwater pits and pipes to install, as well as road pavement and kerb and gutter construction.

We will also be tidying up some private stormwater connections and Telstra pit adjustments on the southern side of Wongawilli Road.

Cadifern are also back in action. They're currently working on the transition pieces, which connect the new and old water main sections. We're working towards getting testing and connection dates from Sydney Water by the end of this month.