Works update 12 July 2021

12 Jul 2021

Culverts and trunk drainage connections - near Shone Avenue

Cadifern are now onsite at Shone Avenue/Wongawilli Road culverts. They will spend the next 3 weeks installing the remaining culverts and trunk drainage storm water pipes. Public pedestrian access through this site has been maintained via a temporary concrete path on the southern side of the road/culvert.

Kerb and gutter pour - from Smiths Lane on Thursday 15 July

Council staff are preparing to pour concrete kerb and gutter at Wongawilli Road from the Smiths Lane intersection, scheduled for Thursday 15 July. We'll need all residents to remove their vehicles from the road reserve/nature strip prior to works on the day. This is to allow access for concrete trucks while the concrete pour takes place. We'll work with residents to help ensure that vehicles are temporarily relocated on the day.

Kerb and gutter - from Bankbook Drive intersection in preparation for final asphalt seal

We've also installed kerb and gutter to formalise the intersection of Bankbook Drive and Wongawilli Road. This is in preparation for the final asphalt seal on Wongawilli Road from Smiths Lane west to Bankbook Drive which will take place in August. The asphalt seal will then allow for parking lane traffic islands and line-marking to be installed along this section of Wongawilli Road.


Share Works update 12 July 2021 on Facebook Share Works update 12 July 2021 on Twitter Share Works update 12 July 2021 on Linkedin Email Works update 12 July 2021 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>