Works update 16 February 2021

This week our crews are continuing road drainage crossings between Smiths Lane and Jersey Farm Road. We're also continuing works at the Jersey Farm Road intersection.

Towards Shone Avenue, Cadifern completed the first section of the base slabs. With good weather we hope to have the culverts for this section installed next week.

We're still waiting for the confirmed water main connection date from Sydney Water. The final pre-connection testing will be undertaken next week. We'll keep the community updated on how we're progressing.

Share Works update 16 February 2021 on Facebook Share Works update 16 February 2021 on Twitter Share Works update 16 February 2021 on Linkedin Email Works update 16 February 2021 link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>