Works update 16 June 2021

Shone Avenue to Smiths Lane

Temporary Road Construction: Temporary road construction is progressing well despite some wet weather delays last week. The asphalt contractor will be on site later next week to seal the new road. Once this is complete we'll switch traffic over. We'll update you next week regarding the timing. Traffic control will be in place during the change-over process.

Trunk drainage: Works are progressing well and will be linked into the previous stage of drainage by the end of the week. Once the temporary road realignment has been completed Cadifern will start works to link drainage into the culverts near Shone Avenue. It's expected that this work will start on 28 June, weather permitting.

Jersey Farm Road to Smiths Lane

Our crews completed the base road pavement construction over the weekend. While cars can now travel on the road, the final asphalt surface will be completed late next week - at the same time as the temporary road asphalt works are being done.


Share on Facebook Share on Twitter Share on Linkedin Email this link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>