Works update 2 February 2021

This week our crews are continuing with kerb and gutter and stormwater works at the intersection of Jersey Farm Road.

We’ve also started sediment control measures and temporary fencing to allow for the installation of the northern side culverts, towards Shone Avenue. Culvert works will commence over the next week, weather permitting.

Cadifern have finished the pressure testing of the water main and we’re now waiting to hear back from Sydney Water about a confirmed connection date. We’ll keep you posted, as soon as we know more.