Works Update 20 December 2021

Since the completion of the final asphalt seal we have been able to undertake work on other parts of the project:

  • Staff have completed the northern side concrete shared path construction from Smiths Lane to Shone Avenue
  • Line marking was completed on Wednesday 8 December as a priority for the safety of motorists and road users. The concrete shared path line marking is to follow
  • Turf and spray grass to the northern concrete shared path has been completed
  • Pedestrian access paths and ramps at the Smiths Lane intersection are nearing completion now that Telstra has finalised the adjustment of their Pits to meet the new footpath levels.
  • Street tree planting has continued along Wongawilli Road, with more to come in the new year
  • Tiger tails are scheduled to be removed by Endeavour Energy on Thursday 16 December

On Wednesday 22 December, staff will vacate the site for the Christmas shutdown. The remaining time leading into the Christmas break will be used to complete minor tasks such as sign installation, repairs to minor defects, site refurbishment and rehabilitation.

Staff will return in the new year to commence the construction of traffic islands between Shone Avenue and Smiths Lane.

This will wrap things up for the year. Thank you again for your cooperation and patience through this extensive work and have a wonderful holiday