This week our works crews are progressing with stormwater and kerb at gutter works at the intersection of Jersey Farm Road.

Cadifern are preparing for pressure testing of the new section of watermain at the eastern end of Wongawilli Road.

Once the testing is completed, Sydney Water will approve connection. While we wait for an approved connection date, Cadifern will make a start on earthworks and slab preparation for the northern side culverts.