Works update 21 June 2021
Shone Avenue to Smiths Lane
Council staff have been constructing the new temporary access road near the culverts at Shone Avenue. This new road layout will enable Cadifern to complete the final installation and connections of drainage culverts and main trunk drainage stormwater pipes.
We're still on track to have Boral onsite this Friday 25 June to undertake asphalt works and to switch vehicle travel lanes to the new alignment. There will be minor traffic delays while this work takes place.
Works will start to ramp up from next Monday 28, once the new road alignment is running, with both Cadifern and Council crews progressing into the next stage of construction.
Jersey Farm Road to Smiths Lane
We anticipate the final asphalt works on Jersey Farm Road will be completed late this week, at the same time as the temporary road asphalt works are being undertaken near Shone Avenue.