Works Update 28 October 2021
Road reconstruction is now well underway with many sections of the project being completed or nearing completion.
The site is still under traffic control with major construction continuing. We would like to ask that you please make sure that you drive to the conditions.
- Smiths Lane intersection will be closed and under detours until asphalt is laid Monday 15 November.
We would also like to reassure you that our staff onsite are very approachable and are more than happy to manage any requests that you may have.
Newly completed work:
- The West bound parking and travel lanes initial asphalt layer completed. (see photo)
This is now two lanes – two way travel for motorists at Wongawilli Road is available while the east bound lanes are under construction.
Nearing completion:
- The final asphalt on the entire Wongawilli Road pavement, Shone Avenue to Smiths Lane, is booked for Monday 15 November, weather permitting.
- Retaining walls are nearing completion with minor general works to be finalised over the next two weeks.
In Planning:
- Street trees have been sourced and are on order with planting scheduled for mid to late November.
- Line marking is scheduled for late November - once asphalt has cured.
- Council staff will commence shared path concrete construction from smiths Lane to Shone Avenue once all asphalt has been completed in Mid-November.