Works update 29 March 2021

Managing the wet weather

We’ve temporarily installed a pump to divert stormwater flows to manage the wet weather and prevent further minor delays to the project. We’re also continuing with installation of the subsoil drainage to ensure any unwanted groundwater is removed from the road pavement.


Kerb and gutter installation - north side between Jersey Farm Road and Smiths Lane

The concrete foundation for kerb and gutter is under construction in preparation for the installation of kerb and gutter on the northern side, which is scheduled for this Wednesday 31 March.

Culverts near Shone Avenue

Cadifern are back on site this week following delays last week with the weather. They're working to prepare the base slabs for the culverts which should be poured before Easter, weather permitting. The next culvert delivery is expected after Easter on Wednesday 7 April.


Trunk Drainage works - south side between Shone Avenue and Smiths Lane

Cadifern has been awarded the contract for the trunk drainage installation works between Shone Avenue and Smiths Lane. We'll be touching base with affected residents this week about these upcoming works. We'll be able to provide more details on the program next week.

Easter Break

Council staff will be off-site from Good Friday on 2 April and returning on Wednesday 7 April.