This week our crews are continuing with kerb and gutter and stormwater works at the Jersey Farm Road intersection and we’ll also be starting road drainage crossings here.

We’ll be undertaking road widening towards Shone Avenue, to ensure 2-way traffic is maintained during upcoming watermain connection works. We’re still waiting on a connection date from Sydney Water.

Cadifern will be on site starting works for the culvert installation near Shone Avenue.