Works update 9 March 2021

Water main connection confirmed for Wednesday 17 March

Sydney Water has advised the water main connection date will be Wednesday 17 March 2021. The shutdown will start in the evening from 9pm and Sydney Water will notify affected residents beforehand. The work will be happening towards Shone Avenue, under traffic control. Residents may see and hear a minor amount of construction lighting and noise.

Once we have completed the water main connection we’ll be able to remove the temporary pipes then install the remainder of the culverts which will be the base of the new road. We’re aiming to have this work completed by Easter.

North side drainage works and preparation for kerb and gutter

Our crews are continuing to work on the drainage on the northern side of Wongawilli Road between Smiths Lane and Jersey Farm Road. This includes the installation of pits, pipes and preparation for kerb and gutter.

Share on Facebook Share on Twitter Share on Linkedin Email this link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>