Works update 8 September 2022
Wongawilli Road
Construction of the new driveways for the RFS station and the community hall is well underway. All the kerb and gutter on the western end of Wongawilli Road has now been completed. Crews will soon begin work on the swale. The swale is designed to collect stormwater runoff and allow it to seep into the soil. We’ll also construct the earth bund wall to divert stormwater towards drainage pits and the swale.
West Dapto Road
A preferred contractor has been decided to undertake the first package of work. The contractor will be setting up and preparing the site mid to late September 2022.
The following photos are of the work that has been undertaken on the western end of Wongawilli Road.